TC Build Pty Ltd v STM123 Pty Ltd [2023] NSWSC 322

Apr 25, 20239 min
--:--
--:--
Download Metacast podcast app
Listen to this episode in Metacast mobile app
Don't just listen to podcasts. Learn from them with transcripts, summaries, and chapters for every episode. Skim, search, and bookmark insights. Learn more

Episode description

“Money down; then you can sue me!”
___
P sued the Ds for $4m claiming it was an unpaid builders margin: [1]
The Ds sought security for their costs: [2]
In 2018 P worked on 2 projects for some Ds, with the Ds’ Dir expressing interest in buying shares in P despite a dropping margin: [7]
Later in 2018 some of the Ds entered into the shareholders deed. One of the Ds became a 50% shareholder in P and P was entitled to charge an 8% margin on costs for construction work done for the Ds: [8] - [10]
In 2019 P began construction work and issued D invoices for costs plus 8%: [12]
The Dirs of P and the Ds incorporated NewCo to do building work. There was some complexity as to whether NewCo charged a margin or was entitled to: [13] - [18]
The Dirs of P and the Ds incorporated NewerCo which, in a complicated arrangement, also purported to do building work for the Ds: [22] - [25]
In 2022, the Dirs of P and the Ds agreed to part ways: [26] - [30]
P then rendered an invoice to the Ds for 8% of the cost of works performed by P, NewCo, NewerCo and related entities: [31]
After settlement negotiations failed, and the making of SOPA payment claims, P commenced proceedings in August 2022: [32] - [39]
The Ds sought financial information from P: [44]
P provided a P and L and said on the assumption its invoices were paid, it was profitable: [44]
P represented that it had tendered successfully for a $20m job, but it appeared that may have been a party related to the P: [45]
The Ds sought security for their costs: [46]
P resisted the application. It said its prospects were strong based on credit findings it said would be made about the Ds’ business practices at final hearing: [50]
P said the Ds’ Dir sent emails requesting invoices be re-issued to refer to other developments, and that contracts were backdated: [51], [52]
The Court said these issues were peripheral to P’s central claim that came from the “complex and changeable” contractual environment: [53]
The Court found that even if the credit finding contended for were made, it was not clear how that would affect the parties’ contractual relationship: [54]
Regarding finances, P said it was $1.4m in deficit. If the $4m claimed was paid its position would stabilise: [56]
The Ds said the claims were claims of other entities related to P, and not P themselves. That meant that P’s prospects were not as strong as claimed and, even if the claims succeeded, the money would not necessarily revert to the P: [57] - [61]
The Court considered whether an order for security for costs would stifle the proceedings.
To prove this, P had to prove neither it, nor those who stood to benefit from the litigation, could provide security. Including due to insufficient evidence about the beneficiaries of a relevant trust, P failed to meet this test: [63] - [71]
The Court ordered that P should provide D with $250K security for their costs, and for it to have its costs of this application: [79]




James